title: A Texas Town of 458 Weighs a Data Center With Its Own Power as State Permits Restart
description: Creedmoor, Texas, is considering a special use permit for a data center by March Capital amidst regulatory changes and community concerns.
image: https://cdn.prod.website-files.com/66525ec138843cc1ccb1c325/68c301ebaa36be33aa2af8f7_1a3f16114a452999cc4d7d6b36ae1602_Obedio%20march%20of%20progress.png
---

[Skip to content](https://hs.getobedio.com/blog/a-texas-town-of-458-weighs-a-data-center-with-its-own-power-as-state-permits-restart#main-content)

[![Obedio logo with black text and an orange graphic composed of four circles and a diagonal arrow pointing up and right.](https://cdn.prod.website-files.com/66525ec138843cc1ccb1c325/66529844eddaa630d6da1b42_obedio%20gold%20for%20white%20background.png)](https://getobedio.com)

[Team](https://www.getobedio.com/team) [Pricing](https://www.getobedio.com/pricing) [Contact](https://www.getobedio.com/demo) [Blog](https://www.getobedio.com/blog) [Login](https://obed.io/v4/login)

Data Center Texas Development Data

# A Texas Town of 458 Weighs a Data Center With Its Own Power as State Permits Restart

![Obedio research](https://7528315.fs1.hubspotusercontent-na1.net/hub/7528315/hubfs/raw_assets/public/mV0_d-cms-elevate-theme_hubspot/elevate/images/avatar-placeholder.jpg?width=48&height=48&name=avatar-placeholder.jpg)

 Obedio research

November 23, 2026

The Board of Aldermen in Creedmoor, Texas, a city of 458 people about 15 miles south of Austin, placed a special use permit for a data center with on-site power generation on the agenda for its November 19, 2026 meeting. The applicant is March Capital. The posted item read: “Discussion and possible action regarding the Special Use Permit for the Data Center and on Site generation used by March Capital.”

It is the third time the request has come before the board since August. It also arrives days after the State of Texas restarted environmental permits for data centers following a pause of nearly two months, while the state grid operator’s audit of data centers is still unfinished, and weeks before a new governor who has promised a moratorium takes office. A local approval would be one step in a longer process rather than the last one.

At a Glance

• **Jurisdiction:** City of Creedmoor, Travis County, Texas (2020 Census population: 458)

• **Applicant:** March Capital

• **Request:** Special use permit for a data center and on-site generation

• **Decision-maker:** Board of Aldermen of a General Law Type A city (mayor and five alderman seats; one seat was vacant as of October)

• **Before the board:** August 20 (presentation), October 15 (public hearing and possible action), November 19 (possible action)

• **Earlier:** Staff workshops on data centers in general on February 5 and May 7, 2026

• **Outcome:** Not yet published. The city had posted no minutes, recordings or agenda packets for October 15 or November 19 as of November 23.

• **State backdrop:** Texas environmental permits for data center projects were paused on September 21, 2026 and resumed on November 16. ERCOT’s audit reports are due December 10, and its pause on grid connections for large data centers continues until its review is complete.

## What the City Has Considered So Far

### February and May: staff workshops on data centers

Data centers were on the board’s agenda before March Capital was. The [February 5, 2026 workshop agenda](https://www.cityofcreedmoortx.gov/media/4006) and the [May 7, 2026 workshop agenda](https://www.cityofcreedmoortx.gov/media/4306) each list a “Discussion with City Staff regarding Data Centers.” Workshops are informational, no action is taken, and the city has not posted minutes for either workshop. The agendas do not name a company or a site.

The city is also rewriting its land-use rules. On July 16, according to the [minutes](https://obedio.ai/g?file=02410260-20260831-cdc681e3d6985fdf2f64b74cfef16295ba3a9dad6ada2d7e2bf59bd242c3ac07.pdf), representatives of Langford, the city’s planning consultant, gave an update on the comprehensive plan and zoning ordinance, presented a draft future land use map, and said finishing the zoning ordinance was important to their current projects. The zoning ordinance posted on the city’s website dates from 2004.

### August 20: an introduction

March Capital first appeared under the board’s reports and presentations on August 20, 2026. The [approved minutes](https://obedio.ai/g?file=02410260-20261006-0ea68eef8dd505149e2e98e6ff669ed9c898416c0d74b70f8d679c762ed2b651.pdf) list the item as an “Introduction presentation regarding possible change of use for onsite data center or manufacturing, presented by March Capital.” A March Capital representative identified in the minutes only as Pete gave a PowerPoint covering the company’s objective, the pros and cons, and the purpose of the data center. The minutes do not record any figures from the presentation. No vote was taken.

The wording matters. The company presented the site as a possible data center or a possible manufacturing use, and it described the request as a change of use, a term that typically refers to a new use for an existing property.

### September 17: not on the agenda, but two related actions

The request was not on the September 17 agenda. At that meeting, according to the [minutes](https://obedio.ai/g?file=02410260-20261102-d16ccd33f539f674fc7d08d8845eb7848a2690fbced0dce5dc4b0606ac2e00ff.pdf), Mayor Jacob Wilhite said the city had received commitments representing more than $2 billion in investments from new developments over the previous eight weeks. He did not name the projects, and the minutes do not tie the figure to March Capital.

The board also voted 4-0 that night to change its zoning change and variance application and notice schedule so that all property owners within 600 feet of a subject property are notified.

### October 15: a public hearing and a possible vote

The [October 15 agenda](https://obedio.ai/g?file=02410260-20261012-7cd3857917b79662605a2c13d5629729fa931ae525c5933c01515ecbd3bb086a.pdf) carried the request twice. Under public hearings, item 2 was a “Public Hearing on Special Use Permit for March Capital, to allow permission for Industrial Center use.” Under action items, item 8 was discussion and possible action on the special use permit “for The Data Center and on site generation use submitted by March Capital.”

The minutes of that meeting are not yet available. The request was posted again for November 19, which indicates the board did not finish with it in October, but the record does not yet say whether it was tabled, continued or discussed without a vote.

### November 19: item 12

The [November 19 agenda](https://obedio.ai/g?file=02410260-20261122-add76eac96aa3907de83fbd0d1d941898a1b97c51d0bb05e42e0d34719b022dd.pdf) lists the permit as item 12. The same meeting included oaths of office for three re-elected aldermen, the selection of a mayor pro tem for 2026–2027, repairs to the city’s septic system, streets and park electrical service, including the solicitation of bids, and a personnel matter concerning the former city administrator and a review of alleged misuse of public funds.

## Who Is March Capital

The city’s records name the applicant only as “March Capital.” March Capital Management has registered five warehouse buildings in Creedmoor with the Texas Department of Licensing and Regulation. Two were registered in 2022 as “March Capital – Creedmoor” at 12610 Wright Road: Building 2 at 188,622 square feet and Building 3 at 200,642 square feet, with estimated costs of $14.2 million and $15.1 million. Both are listed as closed, with the owner given as 45 Logistics South Propco I LLC at the same San Francisco address as March Capital Management. Three more were registered in 2025 under the 45 Logistics South name at 3607 FM 1327 Road, all single-story tilt-wall warehouse shells: Building 1 at 361,976 square feet ($27.1 million estimated) and Buildings 4 and 5 at 66,282 square feet each. Their scheduled completion dates ran from February to June 2026. No tenant is listed for any of the five.

In April 2024, March Capital Management and Deutsche Finance America announced that they had acquired and capitalized the first phase of an industrial park off State Highway 45 Southeast in Creedmoor. Trade press described the full plan as five warehouse buildings with about 900,000 rentable square feet on 61 acres. The park is marketed as 45 Logistics South, at 3607 FM 1327 Road, with access to SH 45, SH 130 and Interstate 35. Leasing materials list the first-phase delivery as March 2025.

The city records do not say which property the special use permit covers, and they do not say whether it involves 45 Logistics South.

## What the Record Does Not Say

The published city records do not state the data center’s power demand in megawatts, the size of the on-site generation or the fuel it would use, the site address, the acreage, the building size, the water source or cooling method, or the end user. The records also do not include any public comments on the request so far. Those details, if they exist, would be in the application and the staff materials. The city does not post agenda packets on its website for any meeting, so neither is online.

## The State Backdrop

A city special use permit controls whether a use is allowed on a piece of land. It does not replace state approvals for grid connection or air permits, and in 2026 those state approvals have been the harder part.

- **Senate Bill 6 (2025).** The law set new rules for large electricity users on the ERCOT grid. Large users must disclose on-site backup generation that cannot export power to the grid and can serve at least half of the site’s demand, and ERCOT can direct those sites to switch to that generation or cut load during a grid emergency. The Public Utility Commission adopted its rule for loads of 75 megawatts or more on September 18, 2026, and it took effect October 8. The rule requires financial security equal to the greater of $50,000 per megawatt of contracted peak demand or the project’s share of transmission upgrade costs.
- **August 3, 2026.** Gov. Greg Abbott directed the Public Utility Commission and ERCOT to audit data centers moving through ERCOT’s interconnection process before any more are approved. Developers must disclose tax incentives, power use and generation, water use and cooling, steps to reduce local impacts, and ownership. Data centers between 25 and 75 megawatts are not part of the pause but must complete a survey on water, energy and community impacts.
- **September 21, 2026.** Abbott directed the Texas Commission on Environmental Quality to pause the issuance of all permits related to data center projects until ERCOT completes its review. In an October 19 letter, the agency said it was screening pending applications and pausing those covered by the directive, and, where possible, suspending data center authorizations that do not require it to issue a permit. On-site generation fueled by natural gas generally needs an air authorization from that agency.
- **No grandfather clause.** Neither directive contains a grandfather clause. The August pause reached only projects still moving through ERCOT’s interconnection process, so projects that had already cleared it went ahead. The September directive applied to pending applications, and the agency’s letter does not address permits issued before the pause.
- **November 2026.** The governor’s office notified the agency on November 13 that ERCOT had finished gathering information from data center projects for its community impact review. The agency resumed its normal permit review on November 16 and that day issued an air permit for a SpaceX data center and gas-fired power plant near Brownsville, according to news and law-firm reports. An agency spokesperson said it “will evaluate applications under all applicable state and federal laws and regulations.” The agency has not posted a notice of the restart on its website, and the November 13 notice has not been published. In announcing the September pause, the governor’s office said data centers must cover all electrical infrastructure costs, result in lower residential electric bills, complete the ERCOT audit, not use water needed by local communities, report electricity and water use, and follow setback requirements that protect nearby communities. The agency has not said whether it is applying those conditions to the permits it now reviews.
- **December 2026.** ERCOT says its audit is not finished. It plans to file two reports with the Public Utility Commission on December 10: a Batch Zero eligibility report that decides which large loads of 75 megawatts or more stay in its first study group, and a community impact report on the water, power, ownership and community information collected from data centers. The commission is expected to take them up at its December 17 meeting. ERCOT’s pause on approving grid connections for large data centers runs until that review is complete. A November 5 preliminary summary showed 433 of 465 projects had responded, covering about 177 gigawatts of requested capacity, with West Texas the largest share at 41%. It gave no figures for on-site generation or water use.
- **January 2027.** The 90th Legislature convenes January 12. Governor-elect Gina Hinojosa, who takes office January 19, has promised an immediate moratorium on data centers until lawmakers write stricter rules, and campaigned on ending data center tax incentives. Abbott has said he will work with the Legislature to end financial incentives for data centers.

A project that plans its own generation is not exempt from this. Building on-site power can reduce reliance on the grid connection queue, but it moves the state approval to the air permit, which is the permit the September directive paused and which the agency resumed reviewing on November 16.

## Why It Matters for Site Selectors and Developers

- Creedmoor has finished industrial space on the SH 45 and SH 130 corridor south of Austin, and the city’s August record shows a property owner weighing data center use against manufacturing for at least one site. How the board handles it will show how the city treats a data center request on industrial land.
- The request pairs the data center with on-site generation in one permit. Any conditions the board attaches, such as limits on generator run hours, noise, fuel or setbacks, will apply to both the building and the power equipment.
- The decision rests with the mayor and aldermen of a city of 458 residents. The board expanded its notice area for zoning changes and variances to 600 feet in September, which affects how many neighbors are notified of comparable requests.
- Whatever the local outcome, the state timeline depends on ERCOT’s December reports, on how the state environmental agency handles data center permits after its restart, and on what the new governor and the Legislature do after January.

## The Risks and Obstacles

- **State rules are still moving.** The records do not name the fuel for the on-site generation. If it needs a state air permit, the application would go to an agency that resumed data center reviews only on November 16 and has not said whether the governor’s September conditions on power costs, water and setbacks apply. If the project would draw 75 megawatts or more from the grid, it would also fall under ERCOT’s pause until the December review is complete. The incoming governor has promised a moratorium after she takes office on January 19.
- **The public record is thin.** Without the power demand, generation size, fuel and site, neither residents nor other developers can yet judge the scale of the project from the published documents.
- **The request has carried over.** The item was posted for action in October and again in November.
- **The city is in an administrative transition.** In August the board engaged new outside legal counsel and approved a forensic financial audit. In September its contract CPA reported that revenue had not been recorded in the city’s books since April and that the city would restart its accounting for the new fiscal year. The November agenda includes a review of alleged misuse of public funds involving the former city administrator.
- **State policy may change again.** A new governor and a new legislative session begin in January 2027, and both the outgoing and incoming governor have called for data centers to pay more of their own costs.

## What to Watch

- The November 19 minutes, which will show whether the board approved, denied, tabled or continued the permit, and any conditions attached.
- The October 15 minutes, which should show what was said at the public hearing.
- Any state air permit filing naming a Creedmoor site or March Capital, and whether it is filed before January 19.
- The terms of the new governor’s promised moratorium, and whether it reaches projects that already hold local approval or pending state permits.
- ERCOT’s December 10 reports, the Public Utility Commission’s December 17 meeting, and the start of the 2027 legislative session.
- Whether March Capital or a partner names an end user or a power figure for the project.
- The board’s next meetings: a possible workshop on December 3 and the regular meeting on December 17, 2026.
- The city’s new zoning ordinance, and whether it adds a data center use or standards for on-site generation.

*This article is factual background and is not legal, financial, or investment advice.*

LinkedIn version — remove before publishing the blog

**A Texas town of 458 is weighing a data center with its own power just as the state restarts data center permits.**

The request first appears in the city’s public record on August 20, when March Capital gave the Creedmoor, Texas Board of Aldermen an introductory presentation on a “possible change of use for onsite data center or manufacturing.” That was nearly two months before the public hearing and three months before the November 19 vote.

The timeline from the city’s own records:

• Feb 5 and May 7: staff workshops on data centers, no company named

• Aug 20: introductory presentation, no vote

• Sep 17: board widens zoning and variance notice to owners within 600 feet

• Oct 15: public hearing and possible action on the special use permit

• Nov 19: the permit is back for possible action as item 12

The state context: Gov. Abbott paused ERCOT approvals for large data centers on August 3, and on September 21 directed TCEQ to pause all permits related to data center projects. TCEQ resumed data center permit reviews on November 16, after the governor’s office told it ERCOT had finished gathering information. ERCOT’s audit reports are not due until December 10, and its pause on grid connections for large data centers continues until then. Governor-elect Hinojosa has promised a moratorium after she takes office January 19. On-site gas generation generally needs a TCEQ air authorization, and the city records do not yet name the fuel.

What the published records do not yet show: megawatts, fuel, acreage, site address or end user.

Obedio reads city council and planning commission records across the country so developers, site selectors and investors see requests like this when they are first presented, not when the vote is reported.

Full article: \[link\]

## Share this post

<https://www.facebook.com/sharer/sharer.php?u=https%3A%2F%2Fhs.getobedio.com%2Fblog%2Fa-texas-town-of-458-weighs-a-data-center-with-its-own-power-as-state-permits-restart><https://twitter.com/intent/tweet?url=https%3A%2F%2Fhs.getobedio.com%2Fblog%2Fa-texas-town-of-458-weighs-a-data-center-with-its-own-power-as-state-permits-restart><https://www.linkedin.com/shareArticle?mini=true&url=https%3A%2F%2Fhs.getobedio.com%2Fblog%2Fa-texas-town-of-458-weighs-a-data-center-with-its-own-power-as-state-permits-restart><https://pinterest.com/pin/create/button/?url=https%3A%2F%2Fhs.getobedio.com%2Fblog%2Fa-texas-town-of-458-weighs-a-data-center-with-its-own-power-as-state-permits-restart>[mailto:https%3A%2F%2Fhs.getobedio.com%2Fblog%2Fa-texas-town-of-458-weighs-a-data-center-with-its-own-power-as-state-permits-restart](mailto:https%3A%2F%2Fhs.getobedio.com%2Fblog%2Fa-texas-town-of-458-weighs-a-data-center-with-its-own-power-as-state-permits-restart)

## Keep reading

### [Local Ordinance Data Center ohio Meta’s 500MW Project Mink Data Center Goes to Licking County Planners With 14 Conditions Attached](https://hs.getobedio.com/blog/metas-project-mink-data-center-goes-to-licking-county-planners-with-14-conditions-attached)

### [Local Ordinance New Jersey Data Center Vineland Council Votes Tuesday on Making DataOne Pay the City's Professional Costs for Its 300 MW AI Data Center](https://hs.getobedio.com/blog/vineland-council-votes-tuesday-on-making-dataone-pay-the-citys-professional-costs-for-its-300-mw-ai-data-center)

[![Obedio your municipal data source](https://hs.getobedio.com/hs-fs/hubfs/google%20workspace-1.png?width=100&height=41&name=google%20workspace-1.png "Obedio your municipal data source")](https://getobedio.com)

Obedio's business intelligence platform provides data and insights from over 25,000 municipalities, enabling retail, manufacturing, finance, real estate, and government clients to make informed decisions, assess risk, and identify opportunities.

<https://www.linkedin.com/company/getobedio/><https://getobedio.com/demo>

**Data Source & Liability Disclaimer:** The data presented on this website is aggregated from various official government and public entities ("The Original Government Sources"). This data may have been modified for use from its original source. The Original Government Sources do not vouch for the quality, accuracy, or timeliness of the data as presented here.

All data is provided "as is." Neither Global Regulatory Risk Advisors, Inc. (d/b/a Obedio) nor The Original Government Sources make any representations or warranties as to the completeness, accuracy, or content of any data made available through this site. All warranties, whether express or implied, including implied warranties of merchantability or fitness for a particular purpose, are expressly disclaimed.

**Usage & Intellectual Property:** While the underlying facts are public records, the specific compilation, organization, and presentation of this information are proprietary to **Global Regulatory Risk Advisors, Inc. (d/b/a Obedio)**. Any unauthorized copying, distribution, or display of this proprietary presentation is prohibited.

 

Copyright © 2018–2026 Global Regulatory Risk Advisors, Inc. (d/b/a Obedio) [|](https://getobedio.com/privacy)[Terms of Service](https://getobedio.com/terms)[|](https://getobedio.com/privacy)[Privacy Policy](https://getobedio.com/privacy)<https://getobedio.com/privacy>

Privacy Policy · Legal · © 2025. All rights reserved.

```json
{
  "@context" : "https://schema.org",
  "@type" : "BlogPosting",
  "author" : {
    "@type" : "Person",
    "name" : "Obedio research",
    "url" : "https://hs.getobedio.com/blog/author/obedio-research"
  },
  "dateModified" : "2026-11-23T19:46:44.782Z",
  "datePublished" : "2026-11-23T19:46:44.000Z",
  "headline" : "A Texas Town of 458 Weighs a Data Center With Its Own Power as State Permits Restart",
  "mainEntityOfPage" : {
    "@id" : "https://hs.getobedio.com/blog/a-texas-town-of-458-weighs-a-data-center-with-its-own-power-as-state-permits-restart",
    "@type" : "WebPage"
  },
  "publisher" : {
    "@type" : "Organization",
    "logo" : {
      "@type" : "ImageObject",
      "url" : "https://hs.getobedio.com/hubfs/google%20workspace-1.png"
    }
  }
}
```

```json
{
  "@context" : "https://schema.org",
  "@id" : "https://hs.getobedio.com/blog/a-texas-town-of-458-weighs-a-data-center-with-its-own-power-as-state-permits-restart#breadcrumb",
  "@type" : "BreadcrumbList",
  "itemListElement" : [ {
    "@type" : "ListItem",
    "item" : "https://www.getobedio.com/",
    "name" : "Home",
    "position" : 1
  }, {
    "@type" : "ListItem",
    "item" : "https://hs.getobedio.com/blog",
    "name" : "Blog",
    "position" : 2
  }, {
    "@type" : "ListItem",
    "item" : "https://hs.getobedio.com/blog/a-texas-town-of-458-weighs-a-data-center-with-its-own-power-as-state-permits-restart",
    "name" : "A Texas Town of 458 Weighs a Data Center With Its Own Power as State Permits Restart",
    "position" : 3
  } ]
}
```