Microsoft Already Has 320 Acres Zoned for Its Gaines Township Data Center. The Rezoning Tabled in April Covers Another 104
Microsoft owns about 320 acres in Gaines Charter Township, just south of Grand Rapids, Michigan, that are already zoned for light industry. In its own filing with the township, the company says a data center is allowed on that land with no special permit. The vote tabled in April is about five other parcels. Together they come to 103.8 acres.
On April 15, 2026, the township Planning Commission voted 7-0 to table Microsoft's request to rezone those parcels. The draft minutes show the public hearing, held in a high school auditorium, ran from 7:31 p.m. to 10:31 p.m. WOOD Radio reported that it ran about four hours, that nearly 600 people came and that 67 spoke. Township records reviewed through October show no new vote on the request.
Microsoft's offered limits on noise, water, lighting and taxes sit in a draft contract tied to that rezoning. If the rezoning never passes, the contract never takes effect. Meanwhile the township has measured the site's noise and set up a committee to write its own data center rules.
At a Glance
- Item: Microsoft's request to rezone five parcels near Patterson Avenue SE, 76th Street SE and East Paris Avenue to Light Industrial, one with a proposed contract of conditions.
- Vote: Tabled 7-0 by the Planning Commission on April 15, 2026. Motion by Commissioner Tim Haagsma, supported by Commissioner Wiersema. No new vote in records reviewed through October.
- Presented by: Jonah Mills, Microsoft's land development manager for the project. Staff review by Dan Wells, community development director.
- Facility/Project: A Microsoft data center campus. Mills told commissioners the buildings would be single-story, about 40 to 50 feet tall.
- Effect: The 103.8 acres keep their current zoning. Microsoft's conditions bind no land yet.
- Payer: Under its offer, Microsoft pays for the water upgrades and grid improvements its project needs. The township manager said a $5,676.97 noise study would be paid from Microsoft's deposit with the township.
- Key figures: 320 acres already zoned for light industry, per Microsoft. 103.8 acres up for rezoning. A 65-decibel noise cap offered. A 39.8 to 55.6 decibel background level measured.
- Fiscal impact: Microsoft says it will not seek local property tax breaks for the land.
- Public outreach: Three meetings on the request postponed before April. A Microsoft open house on March 3, 2026.
What Was Asked, and What Was Tabled
Microsoft asked the township to rezone five parcels. Two sit in a planned zone named for Steelcase, which sold Microsoft much of its land. Three are on 76th Street and are zoned for farms and rural homes. All five would become Light Industrial (LI). For this area, the township's master plan recommends only industry, warehousing and transportation uses with few effects beyond the site.
Only one parcel, 7147 Patterson Avenue SE, would be rezoned with a contract. The draft contract puts it at about 40.5 acres. Microsoft did not own the other four parcels in April. The staff review says it held options to buy them, and the owners did not want their land tied up unless the project goes ahead.
The staff review recommended approval. It found the request met all the township's standards for a rezoning, including fitting the master plan and not hurting nearby property values.
Commissioners wanted more answers first. Haagsma listed noise, the plan for tearing down the site someday, taxes, water and enforcement. Wiersema added low, rumbling sound and vibration. The draft minutes record the motion this way:
Motion by Haagsma, supported by Wiersema, to table the request for a conditional rezoning and allow Microsoft and Township staff to provide answers to concerns posed by the Planning Commission.
The Land Microsoft Says It Can Already Use
Microsoft's application says the rest of its site does not need a vote:
The main parcels, which comprise a total of 320 acres of land, are already zoned LI and are not being rezoned but will be subject to the conditions offered in the Conditional Rezoning Contract. Development of the main parcels for a datacenter is permitted by right in the LI district.
LI is the township's Light Industrial zone. "By right" means allowed with no special permit. The staff review says that when the township updated its zoning code, data centers were treated as a light industrial use.
Microsoft's statement also says the 320 acres have no time limit for building a data center. That is why it asked for 10 years, not the code's default of one, to start work on the rezoned parcels. The filing adds that even the parcels up for rezoning "may already be developed as a datacenter without rezoning," based on earlier interpretations by the township's planner.
The contract's reach is limited. It says its conditions apply to the rezoned parcel and to any land later merged with it or joined to it in an approved site plan. The contract only takes effect once the rezoning does. So the offered limits reach the 320 acres only if the rezoning passes and the land is combined.
What Microsoft Offered
Microsoft listed its offer in a March 18, 2026 letter to Township Supervisor Bob Terpstra and Wells. Similar terms are in a draft contract dated April 2, 2026. The main points:
- Noise: No more than 65 decibels at lines next to homes in normal use, and 85 decibels when emergency generators run.
- Water: No pumping of groundwater for cooling or any other use. The site would use the Byron-Gaines Water System and pay for upgrades it needs.
- Power: Pay its "fair share" for electric service, and pay for grid improvements its data centers need, working with Consumers Energy.
- Taxes: No request for local property tax breaks.
- Screening and light: A planted earth berm or other screen at least 8 feet high, where permitted, next to home lots. Light at the property line held to 0.1 footcandles.
- Setbacks: Server buildings and cooling equipment at least 150 feet from the property line.
- Open space: About 9.5 acres improved and given to the township for open space and trails.
- Shutdown: Microsoft or a later owner is responsible for shutting the site down if it stops being a data center.
Staff flagged two gaps in the April review. First, there was no money set aside that the township could draw on to remove buildings if no new user is found. Second, there was no deadline for Microsoft to combine its parcels, which is what makes the conditions reach the whole site. Staff wrote that Microsoft had been asked to add a removal fund, and that it would change the merger language. A resident letter dated September 21 still describes the request as tabled while the township seeks "more thorough agreements."
What the Noise Study Found
Gaines Township has no noise law. The staff review said so in April: "The current zoning and Township ordinances have no noise limits." So the township hired a firm to measure the site before anything is built.
On August 4, 2026, Township Manager Rod Weersing asked the Board to approve a study by Memtech Acoustics, a firm in Rochester Hills, Michigan. The cost was $5,676.97. His memo said it would be paid from Microsoft's escrow account, money the company has on deposit with the township.
Memtech placed six sound recorders around the site from September 10 to 17, 2026. Its report is dated October 8. On October 12, Weersing told the Board it was on the township website. The main findings:
- The usual background sound on the site ranged from 39.8 to 55.6 decibels. That is the level heard most of the time, not counting short bursts.
- A second set of readings, tuned to pick up low, rumbling sound, ranged from 52.2 to 67.6 on that scale. Memtech warns the two kinds should not be compared.
- The most prominent sources were the warehouses, distribution centers and plants to the north and northwest. On late-night visits, Memtech's staff heard a low hum from that direction.
Memtech also wrote this:
No noise ordinance or criteria were identified for, or provided to Memtech for the Microsoft site.
The township now has a baseline but no rule to measure it against. The only number on the table is Microsoft's offer of 65 decibels. The April staff review described 65 decibels as sounding like "a normal, comfortable conversation."
The Township Is Now Writing Its Own Rules
On September 24, 2026, the Planning Commission voted 5-0 to set up an advisory committee on zoning rules for data centers. Its members are four planning commissioners, Giarmo, Thomas, Wiersema and Rober, plus one township trustee, township staff, and two residents, Tim Lehmann and Phil Bronsma. A second committee will handle general zoning updates.
At the same meeting, Wells said a natural features inventory was done and staff was waiting on the findings. The township calendar listed a meeting of the Advisory Committee on Data Center Ordinance on November 19, 2026, the same day as a Planning Commission meeting. The township had not posted a record of that Planning Commission meeting by November 25. The record does not say whether new rules would apply to Microsoft's pending request or its 320 acres.
The Numbers Do Not Match
Reports on Microsoft's land do not agree.
- Township staff, April 2026: The rezoning covers 103.8 acres. The draft contract puts the contract parcel at about 40.5 acres.
- Microsoft's application: Its main parcels total 320 acres and are already zoned for light industry.
- WOOD Radio, March 4, 2026: Microsoft bought 316 acres from Steelcase for $45.3 million in 2024.
- WGVU News, December 16, 2025: Microsoft bought more than 300 acres from Steelcase for $45 million in October 2024.
- Crain's Grand Rapids Business: Microsoft bought the 316 acres in August 2024, then bought about 40.5 acres next door for $9.7 million in November 2024.
- WOOD Radio, April 16, 2026: Microsoft owns 356 acres and was seeking control of 439 acres in all.
- FOX 17, April 15, 2026: The story's first line says Microsoft wants to rezone "more than 400 acres." Later in the same story it says "over 100 acres."
The Path to Approval, and the Opposition
Two hearings were postponed before April, the staff review says. A February 27, 2025 hearing was postponed at Microsoft's request. A December 18, 2025 hearing was postponed because the crowd was too big for Township Hall. WGVU News reported that more than 250 people came. WOOD Radio reported that a February 12, 2026 special meeting was also postponed at Microsoft's request.
If the Planning Commission sends a recommendation, the Township Board decides. It holds its own public hearing and vote.
Opposition has been steady. On May 11, 2026, 24 residents asked the Board to put their opposition on the record, the minutes say. Many asked for a one-year pause on data centers. A pause stops new projects for a set time. On October 12, six residents spoke against the project, the draft minutes say.
There was support in April, too. John Hartwell, union outreach coordinator for Operating Engineers Local 324, said the project would give his skilled trades workers jobs.
Gaines Township already hosts Switch, which runs a data center campus about four miles north of the Microsoft site, WOOD Radio reported. In a September 24, 2026 letter, Spicer Group asked for a one-year extension of the site plan approval for phase 2 of Switch's substation there. It says this is the last extension the code allows.
Timeline
| Date | Event |
|---|---|
| 2024 | Microsoft buys about 316 acres from Steelcase for $45.3 million (WOOD Radio; Crain's). Month reported as August (Crain's) or October (WGVU). |
| Feb. 27, 2025 | Planning Commission hearing postponed at Microsoft's request. |
| Dec. 18, 2025 | Hearing postponed; more than 250 people exceed Township Hall capacity (WGVU). |
| Feb. 12, 2026 | Special meeting postponed at Microsoft's request (WOOD Radio). |
| Mar. 18, 2026 | Microsoft sends amended rezoning application and list of conditions. |
| Apr. 15, 2026 | Special Planning Commission meeting; hearing runs 7:31 to 10:31 p.m.; request tabled 7-0. |
| May 11, 2026 | 24 residents ask the Township Board to record their opposition. |
| Aug. 4, 2026 | Township manager asks Board to approve $5,676.97 noise study paid from Microsoft escrow. |
| Sept. 10-17, 2026 | Memtech Acoustics records sound levels on the site. |
| Sept. 24, 2026 | Planning Commission creates data center rules committee, 5-0. |
| Oct. 12, 2026 | Manager tells the Board the noise report is on the township website; six residents speak against the project. |
| Nov. 19, 2026 | Advisory Committee on Data Center Ordinance meeting listed on the township calendar. |
| Dec. 14, 2026 | Next scheduled Township Board meeting. |
Why It Matters for Site Selectors and Developers
Most of Microsoft's site does not need a zoning vote, according to its own filing. Even so, the company offered binding limits through a rezoning of the smaller parcels. The draft contract says it would be recorded with the county and run with the land. The rezoning also ties them to a vote the company does not control. Commissioners used the April hearing to ask for changes.
Gaines Township, with no noise law, measured the site before construction. The manager's memo said the cost would come from the developer's escrow account and that the results would be compared with Microsoft's own sound data.
The Risks and Obstacles
The contract in the record is a draft. The conditions take effect only if the rezoning is approved. Staff flagged two terms for revision in April.
There is no noise rule. Memtech found no township noise limit to test against. Microsoft's 65-decibel offer is the only number in play. The new committee may set a different one.
New data center rules are being drafted. The committee formed in September was listed on the township calendar for November 19. Whether its rules would apply to Microsoft's pending request is not stated in the record.
The land is not all owned. Microsoft held options, not deeds, on four of the five parcels, staff wrote in April. WOOD TV reported in March that a 57.8-acre purchase on 68th Street was in progress.
Opposition has not faded. Residents spoke against the project at Board meetings in May and October. Many asked for a one-year pause.
What to Watch
- December 14, 2026: The next Township Board meeting. Watch for any item on Microsoft or data center rules.
- The advisory committee's draft: Any proposed data center rules, including a noise limit that can be compared with Memtech's 39.8 to 55.6 decibel baseline.
- A revised contract: Look for money set aside for building removal and a deadline to combine parcels, the two gaps staff flagged.
This article is factual background and is not legal, financial, or investment advice.