Staunton, Virginia, has no law that bans data centers. Its next big retail deal would ban one anyway.

On November 12, the City Council took up a tax deal for 43 acres. The land sits near Richmond Avenue and Cochran Parkway. A developer, Frontier Center LLC, wants to build a shopping center of at least 200,000 square feet there. In return, the city would hand back half of the new taxes the project creates.

One line in the deal has nothing to do with shopping. "The Phase II Developer agrees that it will not use the property for a data center or any similar use," the draft says. The city's summary of the item points it out on its own: the agreement "explicitly states that the property owner will not use the property for a data center."

The clause comes as data centers have become a hot topic in Staunton. Residents have asked the council to ban them. The city's economic development team is redoing its marketing plan for its biggest job site. That plan once showed a data center.

At a Glance

  • Item: A tax deal for a 43-acre shopping center site. It pays the developer half of the new city taxes the project creates, for 16 years.
  • Data center term: The developer agrees not to use the land "for a data center or any similar use."
  • Vote: The city's Economic Development Authority, a city-created body that makes grants to businesses, approved its side of the deal on November 5. The City Council took it up on November 12. No minutes have been published yet to show what the council did.
  • Developers: Frontier Center LLC, which would build the new phase, and Staunton Frontier LLC, which built the first phase next door under a 2014 deal.
  • Payer: The city. It would pay only out of new tax money the site creates. It does not pledge any existing tax money.
  • Key figures: 43.05 acres. 200,000 square feet of stores, restaurants or hotels. 50 percent of new taxes. 16 years.
  • Recommended by: City Manager Leslie M. Beauregard.

How the Deal Works

Virginia law does not let a city refund taxes to a business directly. So Staunton uses a workaround. Each year, the council gives money to the Economic Development Authority. The authority then passes it on to the developer as a grant.

The amount is based on what the city calls the increment. That is the growth in city taxes on the site after it is built. The deal counts real estate, personal property, meals and hotel taxes, plus the city's share of sales tax. The starting point is what the land paid in the 2025-26 budget year.

Under the draft, the developer gets 50 percent of that growth each year for 16 years. The clock starts when the city approves the first occupancy permit for a store of 50,000 square feet or more. It must start no later than July 1, 2029.

The developer must spend the money on the project. That can include building costs, loan payments and deals to bring in tenants. Each year's payment also depends on the council setting aside the money in its budget.

The city has done this before. In 2014, the council signed a similar deal with Staunton Frontier LLC for about 42 acres on Richmond Avenue. Since then, the city has collected about $9.2 million in new taxes from that land. About $3.9 million went back to the developer. The city kept about $5.3 million.

Why the Old Deal Had to Change

The two sites overlap. The 2014 deal covered part of the land in the new one. So the older developer has to give up its claim to the taxes on that part.

In return, Staunton Frontier LLC asked for two changes to its own deal. Its term would grow from 16 to 18 years. Its share of the new taxes would rise from 40 percent back to 50 percent. It got 50 percent in the first four years. The 2014 deal has seven years left.

Both changes come with a catch. They take effect only if at least 200,000 square feet of stores, hotels or restaurants is built on the new land before June 30, 2033. If that does not happen, the old terms stay.

The Data Center Line

The ban is part of a grant contract, not a zoning rule. Zoning rules apply to all land in a district. This clause binds one developer on one site, as a condition of getting paid.

The draft spells out what happens if a developer breaks the deal. The other side can sue to force it to keep its word. It can seek damages or undo the deal. A developer in default gets no grant payment. It has 30 days to fix a problem after written notice.

The clause also has gaps. The draft does not define "any similar use." It does not say whether a small server room inside a store would count. And the 2014 deal for the land next door has no such line.

Staunton's zoning code already does not list data centers as an allowed use. Mayor Michele Edwards said so in October. "If a proposed industry is not a permitted use, and a data center isn't, it cannot simply bypass our zoning ordinance," she said, as reported by Augusta Free Press. She said any change would need a Planning Commission review, public hearings and a council vote.

The contract adds a second layer. To build a data center there, a buyer would need both a zoning change and a way out of the deal.

The Fight Over Staunton Crossing

Most of the data center talk in Staunton is about a different site.

Staunton Crossing is a city-owned site of about 300 acres where Interstate 81 meets Interstate 64. About 150 acres can be built on. The city bought the land, the former Western State Hospital, in 2009. In 2016 it sold 25 acres along Richmond Road. That land now has two hotels, a gas station and restaurants, Augusta Free Press reported.

The city has spent years getting the rest ready. It has extended Crossing Way, put in water and sewer lines and built a one-million-gallon water tower. The site has earned a Tier 4 rating in Virginia's program that grades how ready a site is to build on.

A 2019 marketing plan for the site showed a data center as one possible use. City officials said in September that no data center is planned, proposed, approved or under review, the Staunton News Leader reported.

On October 8, Tim Davey of Timmons Group, the city's engineering consultant, gave the Economic Development Authority an update. He said the site's expected tax yield had grown from about $12,000 an acre in 2019 to nearly $30,000 an acre. The update included tax scenarios for data centers.

Councilor Jeff Overholtzer, the council's liaison to the authority, asked what terms the city could set if it ever considered one. Davey said the city first had to decide whether it wants data centers at all. If it did, he said, it could work only with the company that will use the building, not with builders who buy land to resell. It could also require deals that give back to the community, limit water use and control generator noise and air quality. If a buyer would not agree, he said, the city would "move on."

Economic Development Director Amanda DiMeo pointed to a different goal. She said Staunton is "uniquely positioned to capture the kind of high-yield advanced manufacturing investments" like recent projects by Merck, Eli Lilly and AstraZeneca. The plan would hold the largest parcel for drug makers, life sciences or advanced manufacturing.

What Residents Asked For

At the council's October 22 meeting, Councilor Campbell spoke first, according to the minutes. He said he expected some speakers to raise data centers at Staunton Crossing. He explained that the authority is thinking about changing its marketing plan and that the council would have to approve any new plan. He asked residents to fill out a coming survey.

Faith Supinger then spoke against data centers anywhere in the city. "Once you catch it, it's too late," she said, according to the minutes. She urged the council to change the zoning code to ban data centers outright.

The council took no action on that request. A ban written into the zoning code would need its own public hearings and votes.

The survey was due out by mid-November. A draft marketing plan is set to go to the authority and then the council in 2027.

Next Door: Augusta County

The county that surrounds Staunton is moving on its own path. The Augusta County Board of Supervisors has voted 5-2 to put up $5,000 toward a regional study of possible data center sites. The money is only spent if the Shenandoah Valley Partnership, the region's economic development group, wins a state planning grant. Supervisors Mike Shull and Scott Seaton voted no. Shull raised concerns about the county's water.

County Administrator Tim Fitzgerald said staff was writing a data center ordinance. It would look at where data centers might or might not fit.

A clause in a city contract does not reach land in the county.

Timeline

Date Event
June 26, 2014 Staunton's Economic Development Authority signs a tax deal with Staunton Frontier LLC for about 42 acres on Richmond Avenue.
2016 City sells 25 acres of Staunton Crossing along Richmond Road for hotels and restaurants.
2019 Marketing plan for Staunton Crossing shows a possible data center.
Sept. 2026 City officials say no data center is planned or under review at Staunton Crossing.
Oct. 8, 2026 Timmons Group updates the authority on Staunton Crossing, including data center tax scenarios.
Oct. 22, 2026 A resident asks the council to ban data centers in the zoning code.
Nov. 5, 2026 Authority votes to enter the Frontier Center deal, if the council approves its part.
Nov. 12, 2026 Council takes up the deal, which bars a data center on the 43 acres.
Mid-Nov. 2026 Public survey on Staunton Crossing expected.
July 1, 2029 Latest start date for the new 16-year grant.
June 30, 2033 Deadline to build 200,000 square feet for the older deal's changes to kick in.

Why It Matters for Site Selectors and Developers

Most cities control data centers through zoning. Staunton is also using its incentive deals. A site that gets city tax help can come with a promise about what it will never be.

That has a cost to the buyer. A tax deal like this runs for 16 years or more. A landowner who signs it gives up a data center option for that long, even if zoning changes later.

For anyone looking at Staunton Crossing, the city has not ruled data centers in or out. Its consultant has laid out terms the city might set. Its mayor has said zoning does not allow data centers now. The survey and the 2027 plan will show which way the city leans.

For investors in retail and hotel projects, the deal shows how Staunton pays for growth. The city puts up no existing tax money. It shares only new taxes, and only if the project gets built.

What Is Still Unsettled

The council's vote is not yet on record. The council took up the deal on November 12. No minutes have been published to show whether it passed.

"Similar use" is not defined. The draft does not say what counts as a use similar to a data center.

Two papers describe the 50,000-square-foot trigger in different ways. The city's summary says Staunton Frontier LLC must build the 50,000-square-foot store. The draft deal ties the trigger to the property and pays Frontier Center LLC.

No zoning ban has been drafted. A resident asked for one. The council has not acted on it.

Staunton Crossing's plan is open. The draft marketing plan will not reach the council until 2027.

What to Watch

  • Council minutes for November 12: Whether the deal passed, and by what vote.
  • The Staunton Crossing survey: Due by mid-November. Watch whether it asks about data centers.
  • A zoning change: Any move to add a data center ban to the city code would go through the Planning Commission and public hearings.
  • Augusta County's ordinance: The county's draft rules on where data centers may go.
  • 2027: The new Staunton Crossing marketing plan goes to the authority, then the council.

This article is factual background and is not legal, financial, or investment advice.