Local Ordinance New Jersey Data Center

Vineland Council Votes Tuesday on Making DataOne Pay the City's Professional Costs for Its 300 MW AI Data Center

Obedio research
Obedio research

City of Vineland, Cumberland County, New Jersey  |  City Council meeting of November 24, 2026

The Vineland City Council will take up Resolution No. 2026-594 at its regular meeting on Tuesday, November 24, 2026, at 5:30 p.m. The resolution would authorize the city to sign a reimbursement agreement with DataOne USA LLC "for professional costs incurred regarding the construction and operation of the AI Data Center at 3963 South Lincoln Avenue."

The resolution comes after a year in which the city issued two stop-construction orders on the site, a state agency fined the developer $1.07 million, and a judge allowed a residents' noise class action to proceed, all while construction continued on what is set to be South Jersey's first hyperscale AI data center.

At a Glance
• Action: Resolution No. 2026-594, reimbursement agreement between DataOne USA LLC and the City of Vineland
• Covers: city professional costs tied to construction and operation of the data center
• Site: 3963 South Lincoln Avenue (Block 7503, Lots 35.01 and 35.02)
• Meeting: Vineland City Council, Tuesday, November 24, 2026, 5:30 p.m.
• Dollar amount: not stated in the posted agenda
• Project: about 300 megawatts, built by DataOne for Nebius, which serves Microsoft

What the Resolution Says, and What It Does Not

The posted agenda lists the resolution by title only. The packet does not include the resolution text, the draft agreement, or a staff report. That leaves several basic questions open until the agreement is released or discussed at the meeting:

  • How much DataOne would pay, and whether there is a cap or an escrow deposit.
  • Which professionals are covered. The title says "professional costs," which in New Jersey municipal practice usually means outside attorneys, engineers, planners and other consultants.
  • Whether the agreement reaches back to costs the city has already spent.
  • How long it lasts. The title covers both "construction and operation," which suggests the city expects costs to continue after the facility is running.

New Jersey's Municipal Land Use Law already lets planning boards charge applicants for the professional review of site plans through escrow accounts. A council-level reimbursement agreement is a separate contract between the city and the company. The title of 2026-594 is broader than site plan review: it refers to the construction and operation of the facility, not to a pending application.

The city has used a similar tool on the same road before. In January 2026, council approved Resolution 2026-13, which amended a reimbursement agreement with Northeast Precast LLC. Under it, the city pays Atlantic City Electric for transmission feasibility studies, including an alternative study estimated at $250,000 to provide 49 megawatts of capacity to a project at 4087 South Lincoln Avenue, and Northeast Precast pays the city back, including a $675,000 second deposit. The resolution does not name DataOne. Northeast Precast's founder helped bring DataOne to Vineland, and the Sierra Club has reported that the company is a minority shareholder in DataOne.

The Project

DataOne, a French data center company, is the owner, builder and operator of the campus. Nebius Group, an Amsterdam-based AI infrastructure company, will run the computing equipment inside, which will support Microsoft's AI services under a reported $17 billion agreement between Nebius and Microsoft. The site, off State Route 55 at Lincoln and Sheridan avenues, was formerly a private industrial park. The complex is usually described as about 2.4 million to 2.6 million square feet.

The site plan has been approved and amended several times. In June 2024, before DataOne was involved, the Planning Board heard an application from NEP Real Estate, the industrial park's owner, for 2,647,628 square feet of data centers, an office building and a parking garage in four phases. The Pinelands Alliance reports that the board memorialized that approval in Resolution 6652 on August 8, 2024. On June 26, 2025, the board approved an amended plan 5-0 that cut the campus from six data center buildings to two and added three natural-gas power generation buildings; the minutes name DataOne USA as the partner that had joined the project. Phase 1, a 129,622-square-foot data center building, was still listed as under construction in the August 2026 hearing notice, although company officials have said at least three data rooms are already online. Phase 2, approved by the Planning Board in August 2026, is the larger part. The hearing notice lists:

  • A 587,980-square-foot, two-story expansion of the Phase 1 building.
  • Nine Bloom Energy fuel cell power areas: four ground-mounted areas of 52,200 square feet each, three two-story platform areas of roughly 104,000 to 111,000 square feet, and two three-story areas of 194,061 square feet each.
  • A 92,466-square-foot chiller building.
  • An 8,660-square-foot liquefied natural gas (LNG) tank area, plus an LNG facility and filling station.
  • A 6,750-square-foot water treatment plant with three treated water tanks.
  • 161,896 square feet of "Megabay" structures in two areas.

The fuel cells would generate most of the site's power on site, using natural gas from an existing South Jersey Gas pipeline, according to WHYY. The LNG tank, reported at 1.5 million gallons, is a backup if pipeline supply is interrupted. At the Cumberland County Planning Board on August 5, DataOne's attorney said the switch from gas engines to fuel cells would avoid DEP air permitting, and described a 27-million-gallon on-site reservoir for misting the equipment bays in hot weather. WHYY reported that the plan needed no variance and is permitted under local zoning. A resident disputed that at the August 11 council meeting, arguing that DataOne's claim to qualify as a public utility in the IB zone does not hold and that a variance would be required.

How the City Has Been Involved So Far

Resolution 2026-594 is one of several council and city actions on the project. The record shows both support and enforcement.

Date Action
June 26, 2024 Planning Board hears NEP Real Estate's original four-phase data center site plan. The approval is memorialized August 8, 2024 (Resolution 6652), according to the Pinelands Alliance.
June 26, 2025 Planning Board approves an amended site plan, 5-0, with DataOne USA named as the project partner.
December 9, 2025 Council adopts Resolution 2025-608, approving city revolving loan funds for DataOne USA LLC.
January 13, 2026 Council passes Ordinance 2026-3 on first reading, 5-0. It authorizes payment in lieu of taxes (PILOT) agreements for several applicants, including DataOne Vineland LLC at 3963 South Lincoln Avenue. Under the city's program, these tax exemptions last no more than five years from project completion.
January 27, 2026 Public hearing on Ordinance 2026-3. Several residents ask council to vote no. Council adopts the ordinance unanimously, according to The Vineland Voice, which reported that DataOne would pay no property tax in its first year of operation, with the share rising 20 percent a year until it reaches full taxes.
March 10, 2026 Cumberland County Department of Health issues a notice of violation for noise above 50 decibels between 10 p.m. and 7 a.m., according to a later lawsuit.
May–June 2026 Neighbors file a federal noise class action on May 26, drop it without prejudice on June 19 after the court questions its jurisdiction, and refile in Cumberland County Superior Court in June. On June 9, council rescinds the revolving loan (Resolution 2026-282) because the loan was withdrawn; DataOne's CEO later said he turned down a city loan of nearly $6.2 million.
August 2026 The city issues two stop-construction orders, saying work began on the LNG tank and fuel cell units without a construction permit. Penalties are $2,000 per violation per day. On August 11, the City Solicitor told council the city had issued the orders and fines and had met with the state Department of Community Affairs.
August 2026 After hearings on August 5 and August 17, the Planning Board approves Phase 2 by an 8-1 vote.
Week of November 16, 2026 Superior Court Judge James Swift denies DataOne's motion to dismiss the noise class action.
November 24, 2026 Council considers Resolution 2026-594, the professional costs reimbursement agreement.

State and private actions have run alongside the city's. On September 22, 2026, the New Jersey Department of Environmental Protection fined DataOne $1.07 million for installing and running 62 natural-gas generators without air permits, which Commissioner Ed Potosnak called the largest enforcement action ever taken against a data center in the state. A DataOne spokesperson said the company disagreed with the determination but would apply for the permits. On October 21, the residents' group Sustain SJ, represented by Earthjustice, sent DataOne, Nebius and Northeast Precast a notice of intent to sue under the federal Clean Air Act. Separately, three neighbors are suing DataOne in Cumberland County Superior Court over noise. Their attorney estimates about 1,000 residents within 1.5 miles could join the class. DataOne argued the noise is temporary construction noise; the judge denied its motion to dismiss the week of November 16, so the case moves to the evidence-exchange stage.

Why It Matters for Site Selectors and Developers

A reimbursement agreement moves a cost from the city's taxpayers to the developer. For a project this size, those costs can include outside legal counsel, engineering review of power and water systems, construction inspection and enforcement. In Vineland, the city also owns its electric utility, which adds utility planning to the list. At the January 27 hearing, one resident asked whether DataOne would reimburse the city for changes and maintenance at the city's Clayville generating station.

For developers working in other New Jersey towns, the Vineland record shows what a host city may ask for after approval, not just before it. The PILOT, the loan, the stop-work orders and now the reimbursement agreement each came at a different point in the project. A developer budgeting a hyperscale site in a small city should expect the city's own review and legal costs to be passed back, and should expect that request to grow when enforcement or litigation is involved.

For other municipalities, the agreement is worth watching. Several South Jersey towns have moved to prohibit data centers, including Commercial Township, which adopted a ban on August 20, 2026, and Vineland has come up in those discussions. A reimbursement agreement is a different approach: the project stays, and the public cost of overseeing it moves to the developer.

The Risks and Obstacles

  • No public terms yet. The agenda gives no amount, cap, term or list of covered services. Without the text, residents and council cannot judge whether the agreement covers the city's real costs.
  • Open state permits. DataOne has said it will apply for the state air permits DEP says were required, and Earthjustice alleges other required permits are also missing. City costs tied to those reviews and any hearings could keep rising.
  • Litigation. A state-court noise class action is moving forward, and a Clean Air Act suit has been threatened. Whether city legal costs connected to those matters would be covered depends on the agreement's wording.
  • Zoning dispute. Residents continue to argue that the fuel cell power areas make the site a power plant rather than a public utility permitted in the IB zone. Any challenge to the Phase 2 approval would add review and legal work for the city.

What to Watch

  • Whether the agreement's text is released and discussed when council takes up Resolution 2026-594 on November 24.
  • The amount, any escrow deposit, and whether costs already spent on the stop-work orders and enforcement are included.
  • Two other resolutions on the same agenda: No. 2026-591, a professional services agreement with McManimon, Scotland & Baumann for legal representation on "environmental matters involving the City of Vineland," and No. 2026-592, an agreement with Brown & Connery for "special litigation services." Neither title names DataOne.
  • DEP action on DataOne's air permit applications and on the $1.07 million penalty.
  • Whether Sustain SJ files its Clean Air Act lawsuit.
  • The city's zoning map and master plan review. In January, the council president said residents' concerns about the code's lack of a definition for AI data centers would be addressed in that review.

This article is factual background and is not legal, financial, or investment advice.

LinkedIn version — remove before publishing the blog

Vineland's council votes tomorrow on making DataOne pay the city's professional costs for its 300 MW AI data center.

Resolution No. 2026-594, on the November 24 agenda, authorizes a reimbursement agreement with DataOne USA LLC for "professional costs incurred regarding the construction and operation" of the data center at 3963 South Lincoln Avenue. The posted agenda gives no dollar amount, cap or term.

This is the latest of several city actions on the about-300-megawatt campus DataOne is building for Nebius and Microsoft:

• December 2025: council approves city revolving loan funds for DataOne (rescinded June 2026 after the loan was withdrawn)

• January 2026: council adopts a five-year PILOT ordinance covering the site

• August 2026: two city stop-construction orders on the LNG tank and fuel cells; Planning Board approves Phase 2, 8-1

• September 2026: state DEP fines DataOne $1.07 million over 62 unpermitted generators

• November 2026: a judge lets a residents' noise class action proceed, and council takes up the professional costs agreement

Obedio tracked each of these in Vineland's council and planning board records as they were posted, from the PILOT first reading in January through this week's agenda. Developers and site selectors can use the same records to see what a host city asks for after approval, not just before it.

Full article: [link]